SCI Website Developent Project

SEMICOLON Inc.

December, 2024




Gantt Chart
December
Milestone Assigned to: Progress Duration 01 02 03 04 05 06 07 08 09 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25 26 27 28 29 30
Project Definition and Discovery
- Set Website Goals Asiful Saky 100% 2 days
- Formulate a Budget Nafis Shahriyar 100% 1 day
- Competitive Analysis Sara Moni 100% 2 days
- Conduct User Research Sujon Mia 20% 5 days
Content Strategy and Architecture
- Gather and Asses Content Rakibul Haque 100% 2 days
- Create a Sitemap Sumi Rani 50% 2 days
- Write Content Sujon Mia 75% 4 days
Visual Design and Prototyping
- Create a mood board Noman Ali 100% 2 days
- Build Out a Wireframe Rownak Jahan 100% 2 days
Website Build and Developent
- Front-end Developent Asiful Saky 75% 12 days
- Back-end Developent Robin Mia 20% 8 days
Final Site Review and Testing
- Testing & Debugging Rownak Jahan 0% 3 days
- Publish the Site John Doe 0% 1 day

Legend:

Purpose Color
Tasks Already Done:
Tasks Done(Portion):
Tasks Haven't Done(Portion) :
Tasks Haven't Started: